Hello Sisters and Brothers,
Grievance Resolution Meetings Scheduled for May
18-CEN-022 Company failed to use the rosters for acquiring manpower for storm duty. (Lines)
18-CEN-024 Two on duty Journeyman Lineman sent home and a contractor (WEEVE) was given the work. (Lines)
19-CEN-006 Responsible Behavior Program (Troubleman)
19-HBG-007 Material ordering, staging, delivery for Substations and Transmission contracted out. (Material)
19-HBG-008 Contractors working storm on overtime and PPL crews not utilized. (Lines)
19-HBG-009 Contractors working storm on overtime and PPL crews not utilized. (Lines)
19-HBG-012 Contractors working storm on overtime and PPL crews not utilized. (Lines)
19-HBG-013 Member on temporary work assignment replaced with contractor at home roster. (Transportation)
19-HBG-015 Contractors working storm on overtime and PPL crews not utilized. (Lines)
19-LEH-008 Management doing Bargaining Unit work. (Electrical Test)
Arbitrations
18-CEN-019 Unjust termination due to violation of rules. (Journeyman Electrician UG) Awaiting Arbitrators ruling.
In closing, I would like to thank everyone for their support and prayers over the past several months while I was going through my cancer treatments.
Take care,
Rusty